Wastewater Treatment Plant Design Engineering

Preserve at Wye Mills Wastewater Treatment Plant Upgrade

Project Description

RAUCH inc. was awarded the Preliminary Engineering analysis contract for review of the existing facilities and preparation of 3-4 or more options for repair or replacement of the existing plant. This included review of MBR treatment add-on units to the existing plant, and exploration of permitting, rights-of-way and sustainability considerations.

The PER contemplated total alternative costing, including debt repayments, life cycle cost analysis, O&M costs, soft costs and construction estimating.  Conclusion and recommendations were offered for best alternative(s).

An add-alternative was included with the report to update the PER for later MDE approvals and funding for the project.

 

Project Details

  • Dates of Service: 2021
  • Preliminary Engineering and Envrionmental Reports
  • Wastewater Treatment Plant Upgrades